HART – Honolulu Rail Transit Project
Farrington Hwy Guideway Construction Update
Farrington Hwy at Waipahu Depot Road
This notice is to update the community about construction in the Waipahu area for the Honolulu rail transit project. To subscribe to weekly construction and traffic updates, please send your request to Waipahu.updates@kiewit.com
Traffic Plans
Estimated Start Date: September 21, 2015
Estimated Duration: 3 months
• Left turns at Waipahu Depot Road on Farrington Highway:
Eastbound – lanes shifts to the right
Westbound – reduced turn lane
• The inside lanes of Farrington Highway will be closed:
Monday to Friday (Saturday as needed)
8:30AM to 3:30PM
7:00PM to 6:00AM
• Two lanes will be open during peak travel times:
Monday to Friday
6 AM to 8:30AM eastbound
3:30PM to 7PM westbound
For questions or concerns, call the HART 24-HOUR HOTLINE (808) 566-2299 or visit www.HonoluluTransit.org